What should a contractor do if their material supplier experiences a strike?

Study for the C53 Law Pool Contractor License Test with multiple choice questions and comprehensive explanations on key topics. Prepare effectively for your exam!

A contractor should contact the owner immediately if their material supplier experiences a strike because effective communication is crucial in maintaining transparency and managing expectations. By informing the owner about the situation, the contractor can discuss the impact on the project timeline, potential delays, and possible solutions. This proactive approach helps in preserving the working relationship with the owner and allows for collaborative problem-solving.

The owner may need to be involved in decisions regarding project adjustments or additional costs. Keeping them informed can help in mitigating any dissatisfaction or confusion later in the process. By taking this approach, the contractor demonstrates professionalism and a commitment to upholding project standards, even in the face of unexpected disruptions.

In contrast, looking for alternative suppliers may be a necessary step, but it should follow the communication with the owner to ensure everyone is on the same page regarding the supply chain issue. Continuing to order materials without addressing the supplier's situation is unwise, as it could lead to wasted costs and further complications. Waiting for the strike to end without taking any action leaves the project at risk of significant delays, which could lead to contractual violations or loss of trust with the owner. Thus, contacting the owner first is a critical and responsible action for the contractor.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy