What approach should a contractor take if they face supplier issues due to labor strikes?

Study for the C53 Law Pool Contractor License Test with multiple choice questions and comprehensive explanations on key topics. Prepare effectively for your exam!

In the scenario of facing supplier issues due to labor strikes, a contractor should prioritize assessing potential alternate suppliers. This approach helps ensure that the project can proceed with minimal delays. Labor strikes can disrupt supply chains and impact the availability of materials, so it is crucial for the contractor to have contingency plans in place.

By exploring alternate suppliers, the contractor can maintain project timelines and avoid the significant setbacks that would occur if they were to stop work or rely solely on the affected supplier. Contacting the owner may be necessary, but it is more effective for the contractor to proactively seek solutions first. Pausing the project could lead to increased costs and missed deadlines, while negotiating better terms with the current supplier does not address the root issue of supply disruption due to the strike. Therefore, assessing potential alternate suppliers is the soundest course of action for maintaining the project’s momentum.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy